Picture Gallery – Construction Phase

On this page you will find pictures of the new building being erected (newest first) which started on Saturday, 13th May 2012.

I will update it as frequently as possible, bearing in mind that this will take place over a longer period of time than it took to demolish the old building!

Latest update: 4th July 2012

The  walls going up - 4th July 2012

The walls going up – 4th July 2012

Ready to build - 2nd July 2012

Ready to build – 2nd July 2012

 

Picture of The footings being laid

The footings being laid – June 27th 2012

 

Picture of the infill process, June 14th 2012

Infilling – June 14th 2012

 

Picture of the retaining wall - 12th June 2012

The retaining wall – 12th June 2012

Picture of the protective coatings applied - 8th June 2012

Protective coatings applied – 8th June 2012

Picture of the first part of the retaining wall - 30th May 2012

The first part of the retaining wall – 30th May 2012

Picture of the cement being poured - 29th May 2012

The cement being poured – 29th May 2012

Pricture - ready to pour the cement

Ready to pour – 29th May 2012

Site view 24th May 2012 - picture

Site view 24th May 2012

Preparing for the big pour - 24th May 2012 - picture

Preparing for the big pour – 24th May 2012

Errecting the steel work - 24th May 2012 - picture

Errecting the steel work – 24th May 2012

The end result! 23rd May 2012 - picture

The end result! 23rd May 2012

The footings for the front wall - 23rd May 2012 - picture

The footings for the front wall – 23rd May 2012

The concrete is laid - 22nd May 2012 - Picture

The concrete is laid – 22nd May 2012

A close look at the steel work - 18th May 2012 - picture

A close look at the steel work – 18th May 2012

Errecting the steel work - 18th May 2012 - Picture

Errecting the steel work – 18th May 2012

Putting up the shuttering - 15th May 2012 - picture

Putting up the shuttering – 15th May 2012

Marking out - 15th May 2012 picture

Marking out – 15th May 2012

Setting the levels – 14th May 2012

Picture - The dice storeage from "Concrete Conkers"!

Is this the dice storage from our “Concrete Conkers” video?

Picture of 25mm concrete screed for level checking

25mm concrete screed for level checking

Picture - The first concrete is down.  Checking levels.

The first concrete is down. Checking levels.

Image of the New Conference Hall

Artists impression of the new Conference Hall

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s