Talking to Paul on site last night, the site workers had had a very wet day yesterday. The rain had lashed down here (just as on the M6 where I was driving to Coventry, and in other places throughout the country) and they were squelching around the site with water to the tops of the wellie boots!
Still, today the mixer was back on site, and more of the foundations have been laid. The pallets laid around the area are for putting the blocks on once building starts.
The revised date for the steel work starting to arrive is now 16th July – so not long to wait before the main structure starts to be erected. meanwhile here is a picture of the site at 16:00 today. Hope you all have a great weekend, and that the weather is much better.